Isnin, 28 Disember 2009

TERMINOLOGY CONTRACT (Istilah Kontrak)

COST. PLUS CONTRACT
-Bahan dan peralatan dibekalkan oleh pihak-pihak berkenaan kepada pemborong

DEVELOPER (PEMAJU)
-Membina lebih 10 unit rumah dan perlu mendaftar dengan kementerian perumahan

VARIATION ORDER (VO)
-Arahan-arahan selepas ditandatangani kontrak , selepas projek -projek dilaksanakan , Lukisan hendaklah diadakan disesuatu bahagian.

PRIME COST ITEM (PCI)
-Kerja-kerja pengkhususan (specially) seperti mekanikal dan elekrikal.
-KOntraktor utama hanya mengambil peratus keuntungan dari kerja-kerja 'PCI'

SENARAI BAHAN (QUANTITIES)
-Dokumen yang ada butiran lengkap termasuk jumlah dan kuantiti

EXTRA OVER (EO)
-Tambahan kos pada kerja-kerja yang lebih daripada kerja-kerja biasa yang dibuat pengukuran, contoh: Facing brick tambahan daripada pengukuran 'Comon brick'

SPOT ITEM
-Item yang dimasukkan didalam kos kerja-kerja yang terdapat di Tapak Bina (Site) contoh: Baik pulih dan meroboh

PROVISIONAL QUANTITIES
-Kerja yang dijalankan oleh kontrator dimana kerja-kerja yang lulus diasingkan daripada bil

SCHEDULE OF RATE
-Jadual untuk memudahkan penilaian penambahan dan pengurangan

PRO-RATA RATE
-Kadar harga berpandukan schedule of rate dan kadar harga yang diubah mengikut perubahan kerja.

AN AGREED RATE
-Kadar harga yang dipersetujui

STANDARD METHOD OF MEASUMENT (SMM)
-Pengukuran piawaian sementara untuk membuat kerja senarai bahan

SPESIFICATION (SPESIFIKASI)
-Penentuan quantiti bahan-bahan dan kerja-kerja dibuat

QUOTATION
-Sebut harga untuk kerja-kerja kecil yang kurang daripada RM50,000.00

LUMP-SUM
-Pukul rata- Pemilihan kontraktor berdasarkan senarai jenis-jenis kerja (Borong Semua sekali)

TAKING OFF
-Kerja-kerja pengukuran daripada pelan yang dimasukkan kedalam borang diamensa (Borang Diamensa)

CONTRACT PRICE
-Harga kontrak yang dimajukan oleh pemborong kedalam borang biling / Dengan memasukkan kerja-kerja seperti jenis-jenis kerja / Harga dan jumlah keseluruhan.

LEARNING PAKAGE (SKM Level 2)

LP 1 DRAWING
-Draw and submit amendment drawing job approval
-Draw detai drawing for given jobs

LP 2 PREPARE FOUNDATION
-Excavate trenches
-Construct timbering and shoring
-Perfome concrete test
-Pour and screed lean concrete on the trenches bed
-Perform pile cap work

LP 3 PEST CONTROL
-Provide pest control services

LP 4 REINFORCEMENT
-Fabricated and place reinforcement in position up to four storey building

LP 5 FORMWORK INSTALLATION
-Erect formwork for ground beam
-Erect formwork for column
-Erect formwork for upper floor beam/roof
-Erect formwork for floor slab
-Erect formwork for arches

LP 6 FORMWORK DISMANTLE
-Dismantle formwork accordingly

LP 7 CURVE WALL CONSTRUCTION
-Construct curve wall
-Construct brick steep

LP 8 HOLLOW BLOCK CONSTRUCTION
-Construct hollow block reinforcement wall and columns

LP 9 RUBBLE WALLS CONSTRUCTION
-Identify and select masonry materials
-Construct random rubble walls

LP 10 ERECT SCAFFOLDING
-Identify and select scaffolding
-Prepare, erect and dismantle independent
-Prepare, erect and dismantle suspended scaffolding
-Prepare, erect and dismantle dependent scaffolding

LP 11 SEWERAGE SYSTEM
-Identify and select material
-Perform installation of sanitation system
-Set the gradient and excavate trenches for sewerage system
-Prepare bed for laying sewerage drain pipe
-Lay and joint pipes
-Set out and construct manholes

LP 12 DRAINAGE SYSTEM INSTALLATIONS
-Set out gradient and dig trenches for drainage
-Lay and joint drains
-Lay and joint culverts
-Construct sump trap

LP 13 OVER HEAD PLASTERING
-Prepared overhead surface for plastering
-Perform plastering for overhead works with finishes

LP 14 SHANGHAI PLASTERING
-Perform 'shanghai' finish on plastered work

LP 15 MOSAIC FINISHING
-Set out and lay mosaic on wall

LP 16 TERRAZZO FINISHING
-Set out and lay precast terrazzo
-Set out and perform cast in situ terrazzo
-Perform grinding and polishing work on terrazzo

LP 17 MARBLE FINISHING
-Set out and lay square marble
-Set out and lay broken marble
-Perform grinding and polishing work on marble floor

LP 18 NON MASONRY PLASTERING
-Perform plastering works on non masonry structures and special purpose

LP 19 PARQUET FINISHING
-Set out and lay parquet on floor
-Perform grinding and polishing work on parquet floor

LP 20 POLYVINYL FINISHING
-Set out and lay polyvinyl chloride tiles

LP 21 MAINTENANCE
-Identify types of building services required
-Detect and repair minor defects.